A foundry audit is not a factory tour with better vocabulary. Every iron foundry melts metal and pours sand; what separates a supplier you can send a pressure part to from one you cannot is what happens between those two actions — how the melt is verified, how the sand is controlled, and what the certificate actually attests.
This page gives an on-site checklist in the order that finds problems fastest, the documents to request before you fly, and the red flags that end an audit early.
Ask for five documents and read them against each other.
The cross-check is where desk audits earn their keep: does the certificate's chemistry include magnesium and the nodularizing evidence? Does the tensile sample match the wall band your part would need? Does the dimensional report show scatter or just verdicts? A brochure claims capability; these five documents either support it or quietly contradict it.
The melt shop decides the material, and it is the hardest department to fake. Check the spectrometer — present, in use, calibration stickers current, and standards for magnesium and carbon equivalent visible in the daily routine. Ask to see a wedge sample or thermal analysis record from the last shift; carbon equivalent control is the difference between a foundry that manages chemistry and one that reacts to it.
Then ask the uncomfortable question directly: what happens when a heat fails the tensile test? The right answer involves retests per the standard, heat traceability, and a decision rule that ends in remelt. A vague answer about "adjusting" the following heat is a finding, not an answer.
Nodularizing practice is the next check. Magnesium treatment is time-sensitive — the treatment ladle, the sinking of the reaction, and the check that magnesium recovery happened belong in a repeatable sequence. Watch one treatment if scheduling allows; it is the single most revealing ten minutes in a ductile iron foundry.
Green sand is a live chemistry: moisture, compactability, active clay, loss on ignition all drift and must be measured every shift, not every audit. A sand lab with current test records and an operator who can explain the last corrective action is a good sign. An empty sand lab with a calendar from two months ago is a finding.
On the moulding line, look at mould hardness measurements, mould weight checks on the vertical line, and how cores are stored and handled. Then look at a freshly poured mould sequence with the part in mind: does the gating match what the first-article package showed, or has the shop drifted to whatever works that week?
The QC lab should show tensile machines with calibration, hardness testers with test blocks, and metallography — because ductile iron quality is nodularity and matrix, and a foundry that cannot read its own microstructure is selling you its average luck. Ask to see a polished sample and the reading: nodularity per EN ISO 945 forms, pearlite percentage, graphite count.
NDT capability matters by need: UT on heavy sections, MT for surface cracks, RT where radiographs are specified. The equipment should be operated by certified staff, and the report format should carry actual readings with acceptance criteria named.
The certificate question closes the audit. EN 10204 3.1 certificates are issued by the manufacturer's own authorized inspector against the order's requirements; 3.2 adds an independent inspector. A supplier who offers 3.2 for everything is either over-servicing or does not know what it costs them; a supplier who cannot produce a 3.1 traceable to a specific heat and casting number is under-servicing. Both are findings.
Any two of these together should end the visit and the evaluation. One is a finding to fix before the first order; six is a decision already made.
The audit is half the evidence; a first article is the other half. Evaluate it as a package rather than as a bare part: dimensional report with real values and scatter, certificate matching the sample type your wall band requires, metallography if the application justifies it, and the simulation or feeding plan on a new part. A first article that arrives with a packing list and nothing else tells you the audit questions were polite.
The strongest suppliers will send the first article with the documents you did not ask for — the wedge record, the sand lab log for the pouring shift, the UT map. That habit, more than any single certificate, is what a good audit is looking for.
How long does a foundry audit take?
One full day for a capable auditor who knows iron: melt shop in the morning, sand and moulding mid-day, QC and certificates in the afternoon. Anything shorter becomes a tour; anything longer should be a technical review with the specific part on the table.
Is ISO 9001 enough?
It proves a management system exists, not that the metallurgy is controlled. The melt shop and lab checks carry more weight for castings than the certificate itself. Sector standards add requirements where the application demands them.
What is the single most important check for ductile iron?
Nodularizing control and its verification — magnesium recovery confirmed by wedge or thermal analysis each heat, and microstructure read in-house. A foundry that cannot see nodularity is shipping averages.
Do I need to audit before every supplier?
Before the first order, yes, scaled to the risk: a full day for pressure and safety parts, a shorter visit or desk audit for non-critical components. Re-audit on schedule or after a major change in process or ownership.
What documents should accompany production shipments?
Mill certificate per heat with the sample type stated, dimensional report per agreed sampling, NDT reports where specified, and repair records when the drawing permits repairs. The audit sets the format; production repeats it.
Can a trading company pass a foundry audit?
Only if it brings the producing foundry and its records. The checks above — spectrometer in daily use, sand lab, nodularity reading — are physical, on the pouring floor. Ask where the metal is melted and audit there.
Send the part drawing, the grade and standard with sample type, the NDT and certificate requirements, and the annual volume. The supplier who can answer those in writing before you arrive is the one whose floor will match the paperwork when you walk it.
Related reading: our foundry process and capacity, ductile iron casting properties and grade data, ISO 8062 casting tolerances, and ductile iron casting price per kg.